• 2014
  • Acquisition of Project

    May - August 2014

    Pantoro acquired the Nicolsons Project and began a 12 hole confirmatory drill program.

  • Feasibility & Finance

    September 2014 - February 2015

    A feasibility study was completed with production of 25 - 30,000 ounces per year. Bank finance was obtained and Project permitting was completed.

  • 2015
  • Refurbishment & Construction

    February - September 2015

    The processing plant was substantially refurbished and mine construction started. First gold was poured.

  • 2016
  • Feasibility Run Rate Achieved

    March 2016

    Pantoro hit the feasibility run rate production level.

  • Expansion Plans

    July 2016

    Pantoro announced its plans to expand production at Nicolsons to 50 - 55,000 ounces per annum.

  • Open Pit Mining

    October 2016

    Open pit mining at Wagtail commences.

  • 2017
  • Increased Production Achieved

    July 2017

    The increased production target of 50 - 55,000 ounces per annum was achieved.

  • 2018
  • Acquired Regional Projects

    February 2018

    Pantoro acquired the Grants Creek and Mary River Projects.

  • Ore Sorter & Second Underground Mine

    June 2018

    An ore sorter and upgraded crushing circuit was added to the Nicolsons processing plant. The second underground mine at Wagtail commenced.

  • Future Development